The state started a $5 million dredging project at Lahaina Harbor this week, marking one of the most expensive repairs still needed before full reopening by end of 2027. Eight commercial tour companies now have limited access to the harbor.
- A $5 million harbor dredging project began this week and is scheduled for completion in December 2026.
- Eight commercial companies now have permitted access to the harbor, up from four in December 2025.
- Harbor hours expanded to 6 a.m. to 6 p.m. with further adjustments planned for summer daylight hours.
- The most expensive repairs are still ahead, including $8 million for pier work starting October 2026.
- Full harbor recovery is not expected until the end of 2027, nearly four years after the August 2023 fire.