County reconstruction work will close sections of Makawao Avenue on weekends through June 21, 2026, with local traffic access only during 6am Saturday to 6:30pm Sunday closures.
- Weekend closures affect different Makawao Avenue sections each weekend from May 16 through June 21, 2026.
- Local traffic access will be maintained during full weekend road closures from 6am Saturday to 6:30pm Sunday.
- Memorial Day weekend (May 23-24) will have no closures scheduled.
- Weekday construction continues with single-lane closures from 8:30am to 3pm between Apana Road and Ai Street.
- The overall reconstruction project runs from October 2025 to February 2027, upgrading 1.8 miles of roadway.
Source: Maui Now